| Key
Info |
| Purpose:
Construction of new clad
steel framed structure |
| Location:
Rugby |
| Project
Duration: 4 Months |
| Completion Date:
Jun 2011 |
| Project
Cost: £108,149 |
| |
|
|
| Project
Overview |
Construction
of new metal-clad steel-framed
structure to house new electrical
transformers at Ball Packaging's
factory in Rugby. Working to
a tight time-frame to allow
for the changeover of transformers
during the factory's shutdown
period, the structure was constructed
in a testing environment with
the nature of the size of the
transformers, the overhead power
supply and the switchover logistics.
|
|